New Siemens Inter City Trainsets (ICT)

Help Support Amtrak Unlimited Discussion Forum:

west point

Engineer
Joined
Jun 9, 2015
Messages
3,346
Location
SW ATL airport
Thanks gentlemen. I had my suspicions that the Albany and beyond trains with batteries in the battery car were designs not finalized. If or not there is a powered truck on front truck will affect many operational possibilities as well. As you pointed out will there even be seats? The only item for sure seems to be no CAT PAN. However, there seems to be no reason that a CAT equipped train could not go to Albany as CAT is installed to the end of the west side access tunnel at NYP? But the Battery car trains do have the advantage of being able to go to NYG.
 

frequentflyer

OBS Chief
Joined
Jun 10, 2008
Messages
999
So on a NYC-RIC train, will the diesel motor be turned on at NYC or at WAS when it leave the electrified area?
 

NES28

Train Attendant
Joined
Jan 18, 2019
Messages
91
It would be really good to electrify the First Street tunnel, just south of Washington Union Station, to resolve the smoke problem.
 

west point

Engineer
Joined
Jun 9, 2015
Messages
3,346
Location
SW ATL airport
Once Amtrak completes the forced acquisition of WASH union station from the present leese then items can be done that the present leese will not cooperate. One item mentioned is Amtrak says immediate work on the 1st street tunnel is needed. That may include your electrification. Of course, only if Superliners will clear the CAT enough. Actually, using a conducting rail insulated against the celling is a real possibility. Done at many rail locations worldwide.

That might be workable depending how long a warmup is required for the diesel prime mover. It may be that the connection to the CAT at WASH will allow warmups if the diesel has some kind of heater(s) for the diesel coolant.

It would be really good to electrify the First Street tunnel, just south of Washington Union Station, to resolve the smoke problem.
 

jis

Chief Dispatcher
Staff member
Administator
Moderator
Gathering Team Member
Joined
Aug 24, 2003
Messages
32,325
Location
Space Coast, Florida, Area code 3-2-1
That might be workable depending how long a warmup is required for the diesel prime mover. It may be that the connection to the CAT at WASH will allow warmups if the diesel has some kind of heater(s) for the diesel coolant.
NJT has been transitioning from electric to diesel for years through many winters on their ALP45DPs. I do not recall them running the diesels for a very long time before transitioning. I would be surprised if the Siemens ones would be much different.
 
Last edited:

NES28

Train Attendant
Joined
Jan 18, 2019
Messages
91
Does anyone know what the clearance is in the First Street tunnel?
 

jis

Chief Dispatcher
Staff member
Administator
Moderator
Gathering Team Member
Joined
Aug 24, 2003
Messages
32,325
Location
Space Coast, Florida, Area code 3-2-1
Does anyone know what the clearance is in the First Street tunnel?
My guess is it is at least 16'6" above rail since Superliners are known to operate through there without scraping the roof. So there is enough dynamic clearance for them. But that does not mean there is space for catenary necessarily.
 

keelhauled

OBS Chief
Joined
Oct 3, 2014
Messages
875
Location
Camorr
NJT has been transitioning from electric to diesel for years through many winters on their ALP46DPs. I do not recall them running the diesels for a very long time before transitioning. I would be surprised if the Siemens ones would be much different.
As long as there's electricity in the trainset, it should be trivial to have a coolant heater for the diesel.
 
  • Like
Reactions: jis

rickycourtney

Conductor
Joined
Dec 21, 2012
Messages
1,898
Location
Fresno, CA
Two interesting infographics making their rounds on social media today…

intercity_trainset_configurations.jpg

intercity_trainset_power_control_features_02.jpg
 

west point

Engineer
Joined
Jun 9, 2015
Messages
3,346
Location
SW ATL airport
It is puzzling that Amtrak will use battery pack train sets on the Empire corridor. A 1- or 2-mile extension of NYP CAT north of present end on the west side line would seem easily done unless the diesel engines have a long warm up time. One reason might be Amtrak does not want to worry if there is a CAT failure at NYP. Also, the battery pack trains could be used as a Hudson River rescue train instead of using the third rail equipment in those tunnels. The other item might be that battery pack trains could detour to GCT on very short notice. It is also a possible to use the battery pack trains for lay over in Albany. My take it would be better to string a short section of CAT to provide overnight current at Albany.
 

Mailliw

OBS Chief
Joined
Jun 14, 2020
Messages
590
Location
Scranton, PA
Overall I like what I see, but the food service cars should be placed in the middle of the trainset, not right after Business Class. On the NER Coach passengers could have to walk (or  wheel) through up to six cars! 😲 Not good. If Amtrak is soo worried about BC passengers having to walk through a few cars just hire a BC attendant.
 
  • Like
Reactions: Cal

jrud

Service Attendant
Joined
Feb 12, 2018
Messages
151
Is anyone else seeing information that the batteries will take up more of the car than the pantograph? I’ve seen an unofficial drawing with batteries taking the whole car. Plus speculation that batteries will require additional length.

I’ve also not seen anything indicating the battery car will have a driven truck like the pantograph car does. Has anyone else heard otherwise?

Finally, the 2022 NGEC presentation seems to indicate that only the pantograph car is called an APV and the battery car is just called a battery car. Is there any other “official” information on the naming?
 

joelkfla

Conductor
Joined
Oct 16, 2018
Messages
1,777
Location
12 miles from Walt Disney World
Is anyone else seeing information that the batteries will take up more of the car than the pantograph? I’ve seen an unofficial drawing with batteries taking the whole car. Plus speculation that batteries will require additional length.

I’ve also not seen anything indicating the battery car will have a driven truck like the pantograph car does. Has anyone else heard otherwise?

Finally, the 2022 NGEC presentation seems to indicate that only the pantograph car is called an APV and the battery car is just called a battery car. Is there any other “official” information on the naming?
The infographic above calls both Auxilliary Power Vehicles, shows both including BC seating, and says the pantograph APV has a powered truck but says the battery APV sends power to the locomotive with no mention of a powered truck.

ETA: But I just saw @jis's reply saying he doesn't think it's official.
 