Good news. However, I am wondering if they are going to do this project in a couple of phases. The last cost estimate I can recall was somewhere around $750M. I guess I will have to dig around on the CREATE sight and see if it has anymore details.
Yes, the entire 75th Street Corridor Project will be completed in phases.
The $132 million they received ($160 million requested) in INFRA grant money will go towards final design and construction of the Forest Hill (CSX) flyover, grade separation at 71st Street, just east of Western Avenue (Bell Ave./2200W), and improvements to Argo Yard and Argo and Canal Junction. Final design (but not construction) of Belt Junction and 80th Street Junction improvements, as well as the flyover for Metra-Southwest Service trains, were also part of the request in the INFRA application.
According to the INFRA application, the anticipated timeline for the corridor improvements (pending funding) is as follows-
-Argo Improvements complete by April, 2020.
-Belt Junction and 80th Street Junction Improvements complete by April, 2023.
-Forest Hill flyover and 71st Street grade separation complete by June, 2023.
-Rock Island Connection (Southwest Service flyover) complete by November, 2023.