west point
Engineer
Have to wonder if Amtrak is going to keep its present method of HEP for the new car orders. Amtrak could install the VIA method of HEP distribution. As I understand it the VIA system can work together with present Amtrak cars but only use the Amtrak method of distribution. However, to use the VIA method that uses 2 locos and cross over power to every car all cars must only be the VIA method ,Actually the real showstopper is the design limit of 1200kW of the cabling. It is not that hard to create a small subfleet of ALCs with 1200kW HEP Inverter replacing the 1000kW HEP Inverter.